Minutes:
Councillor Kent queried the purpose of the
report. The Chair stated that the issue of compensation had not
been discussed by the Task Force previously and gave the
opportunity for officers to answer questions and provide comment.
The Senior Consultant Stantec introduced the report and stated that
compensation given by National Highways (NH) was divided into two
parts: the first was statutory compensation that had been contained
within section three of the Council’s formal consultation
response; and non-statutory compensation.
The Senior Director CBRE stated that compensation could also be
given in three instances where no land was taken from a
resident:
a. Section 10 of the Land Compensation Act
(commonly known as the McCarthy Rules) which were only applicable
where a right benefitting retained land was impacted causing
reduction in the value of retained assets. He gave an example of if
a resident had their access rights impacted by the scheme, which
subsequently reduced the value of their house, then they might be
entitled to compensation for the reduction in value arising from
the executive of the works. He explained that NH would often negate
a claim by re-providing the right (in the example by providing an
alternative access to the house).
b. Noise insulation regulations, which were only
available to houses within 300m of the scheme and where:
i. The ‘Relevant Noise Level’ was at least 68 dB(A)
L10(18 – hour).
ii. The ‘Relevant Noise Level’ was at least 1 dB(A)
more than the
‘Prevailing Noise Level’.
iii. New roads would contribute at least 1 dB(A) to the
‘Relevant Noise Level’.
He stated that the compensation offered under these regulations
would be to mitigate the impact of the noise, for example by
offering to pay for double or triple glazing, or other noise
reducing works. He added that the noise threshold of 70 decibels
was extremely high, and therefore only limited residents were
likely to qualify for compensation under these regulations.
c. Part 1 of the Land Compensation Act 1973, which
compensated the owner of a house or interested land for the reduced
value of their asset caused by physical factors arising from the
use of the works. He stated that these physical factors included
noise, smoke, dust, and fumes, but did not take into account loss
of views. He stated that this compensation could only be accessed
one year after LTC scheme opening, and residents either had to own
the freehold to their property or have a long leasehold interest in
rented property to apply. The Senior Director CBRE stated that it
would be difficult for residents affected by the construction of
the route to claim compensation, and non-compulsory purchases would
not be regularly offered, even if residents were affected by noise,
dust or traffic.
The Chair sought clarification that non-statutory compensation
would not be widely available during the construction phase, and
queried how many properties in Thurrock would be negatively
affected by the construction. The Senior Consultant replied that NH
had undertaken an exercise to identify all properties within 300m
of the proposed route, and one of the Hatch measures had been to
ensure that earthwork construction, where residents lived 300m or
less from the route, would be limited to daytime hours, and the
team would try to secure this in the Development Consent Order
(DCO), agreed by NH. He added that NH had plans outlining all of
the affected properties, but were currently updating their noise
and air quality assessments before determining if mitigation to
those residents would be required. The Senior Director CBRE added
that it was difficult to assess some of the impacts, as the
majority of the design had not yet been agreed, and much of the
design work would be left to the contractors. He stated that the
LTC team in Thurrock were working to foresee potential issues
before they arose and ensure mitigation measures against these
issues were included in the DCO.
Councillor Muldowney explained that she had had a discussion with
the NH Executive Director for LTC and had requested a fund be
set-up for those residents living close to the route who suffered
from COPD or other illnesses that could be worsened by their
proximity to the route. She mentioned that this fund could be used
to relocate, either temporarily or permanently, these residents to
ensure their health would not be impacted by the scheme. She
queried if any progress had been made on developing this fund. The
Senior Consultant replied that her suggestion of the fund had been
included in the original comments submitted as part of the
non-statutory Community Impacts Consultation, but the team had not
yet received feedback on these comments. The Senior Director CBRE
stated that he had previously worked on the HS2, Heathrow, and
Thames Tideway schemes and these had been run by the private sector
where enhanced compensation had been offered. He stated that as NH
were a government organisation it tended to only offer the
statutory minimum level of compensation required.
The Thames Crossing Action Group (TCAG) Representative asked if the
compensation schemes could be accessed by the general public, as
well as by the Council. The Senior Director CBRE replied that any
property within 300m of the scheme would be eligible to apply for
compensation. He stated that these compensation claims usually fell
within part 1 of the Land Compensation Act, and there were
companies that specialised in helping people affected by these
schemes apply for that compensation. He stated that they often mail
dropped a local area that would be impacted, and although they
could offer their assistance, there was no guarantee that a
compensation claim would be successful. The TCAG Representative
asked if residents whose properties did not fall within the red
line boundary could apply for compensation. The Senior Director
CBRE replied that they could apply for compensation, for example if
their access was affected by the construction works, but it was
difficult to judge the value lost in these houses due to the
scheme. He added that if residents who suffered from COPD and other
long-term conditions were concerned about the impact of the scheme,
they could apply for a discretionary purchase order under the
Highways Act, but they had to have a compelling case that would
explain their need to move due to the scheme, and the bar was set
very high for this type of compensation. The Chair questioned if
there was a time-limit to apply for a discretionary purchase order.
The Senior Director CBRE replied that there was no time-limit, but
it was prudent for residents to act quickly as soon as the
circumstances arose, as it would take time for their application to
be submitted, processed and a price agreed upon. The TCAG
Representative stated that if residents were concerned, basic
information could be found on the TCAG website.
The Senior Director CBRE left the meeting at
6.25pm.
Supporting documents: