Minutes:
The Senior Consultant Stantec introduced the report and stated nineteen
fortnightly meetings had now been held between the Council and
National Highways (NH). He stated that the team had had some
measure of success in agreeing some of the mitigation measures, and
the Hatch report would contribute to the Statement of Common
Ground. He commented that NH had started an ‘issues
log’ which had recently been re-evaluated and now
incorporated all of the comments made by Thurrock Council in
previous consultations and on most technical documents. He
explained that the issues log had been grouped into three sections,
the first including duplications, statements and issues which had
been superseded or were of no consequence anymore. The Senior
Consultant explained that 1100 issues were included in this section
and Thurrock Council would be likely to agree to about 90% of them.
He stated that the second section included technical matters, which
was made up of 1,500 issues, the majority of which were still under
discussion and needed review. He stated that the third section was
made up of 400-500 significant issues between NH and Thurrock
Council that needed further detailed discussions or agree to
disagree. He explained that these would be discussed in the New
Year, although Thurrock will try to identify a summary of 20-30
important issues, and possibly 5-6 critical issues.
The Senior Consultant stated that the Hatch report update was
colour coded. He commented that there were 5 purple measures, which
meant NH had declined these and considered that these should not be
challenged as they largely fell under the remit of the Department
for Transport. He explained that there were 17 red measures which
were currently unresolved issues, which had not yet been resolved
even after numerous meetings. He felt that NH were happy to make
minor amendments to these measures, but would not make any
amendments that would result in a significant change for the scheme
or programme. He explained that there were 20 amber measures, which
were close to agreement. He stated that therefore 37 out of the 58
issues, approximately 70%, were rated as either purple, red, or
amber. He summarised and stated that the measures marked as green
in the report had not been formally agreed yet, but were
technically acceptable. He added that although there had been
progress on the Hatch report, this was mainly at a lower
significance level.
The Chair asked for clarification regarding the purple measures.
The Senior Consultant stated the purple measures were: smart speed
limits as NH would only consider these on a regional level; revised
proposals for the A13 junction; a fixed proportion of tolls for
hypothecation (as this was the remit of the Department for
Transport); the provision of legacy worker accommodation; and a low
emissions target and financial penalties payable to Thurrock
Council if these were missed, which would require Department for
Transport approval. The Interim Assistant Director Regeneration and
Place Delivery added that these purple measures were being
discussed with both NH and would be raised directly with the
Department of Transport. The Senior Consultant replied NH,
including the Executive Director, had declined these purple
measures, such as legacy worker accommodation. He stated that the
team were concerned that 400 on-site worker units and 80 hyperbaric
units would not be enough to accommodate all workers, and this
would place additional stress on the local rental market or local
road networks due to increased commuter numbers.
Councillor Muldowney questioned measure M4 relating to air quality
sensors along the route during construction, and asked if these
would remain during route operation. The Senior Consultant replied
that NH were proposing to install air quality monitors at certain
agreed locations along the route, but Thurrock were pushing for
these air quality monitors to remain during operation, as the
Council would then be able to compare current baseline air quality
data and could agree any exceedances with NH. He explained that NH
did not want air quality monitoring during route operation, as
their models told them that emissions would be negligible so there
would be no need to monitor. He added that legislation had recently
changed which meant mitigation for nitrogen dioxide needed to be
accommodated, so Thurrock would be pushing for monitoring during
this operation. Councillor Muldowney questioned the measure M5 and
asked what the core hours of operation would be, and if any
progress had been made on this measure. The Senior Consultant
replied that the Code of Constriction Practice outlined core hours
at 7am to 6pm with an hour before and after for mobilisation and
demobilisation. He stated that Thurrock had been pushing for a
reduction in using extended hours until 10pn during long summer
months for earthworks where the route passed close to houses, and
NH had undertaken GIS mapping to identify areas where properties
came within 300 metres of the centre line of the route, and had
agreed to only work during core hours in these areas. He stated
that this would mostly benefit communities in Linford and Chadwell
St Mary, but highlighted that some areas of the route construction,
such as all tunnel works or utility works/bridge installation,
would need to be 24 hours for safety reasons.
The Resident Representative stated that the majority of noise
emissions would be from HGV movements, and NH were predicting
approximately 400-500 HGV movements per day. He asked if these had
been included in noise calculations, and asked if these HGV
movements would be following pre-planned routes. The Senior
Consultant responded that noise mitigation measures may not include
HGV movements, but these would be limited to core working hours and
would be outlined in the DCOv2 submission. He stated that the
construction model revised HGV movement routes, but Thurrock
Council were working to restrict HGV movements around the borough,
which would necessitate NH increasing use of the river, ports and
surrounding haul roads and the LTC ‘trace’. The Chair
asked why the measure regarding noise mitigation was red. The
Senior Consultant replied it was because no noise data had been
received yet, so Thurrock were unable to make comment or propose
specific mitigation measures.
Councillor Muldowney highlighted measure M7 and queried what carbon
neutral would mean in terms of the scheme. The Senior Consultant
replied that it did not necessarily mean electric vehicles, but
meant no petrol or diesel vehicles in certain circumstances. He
explained that this could mean hydrogen vehicles, or the use of
other new carbon neutral vehicle technology that was currently
being developed. Councillor Muldowney questioned measure M13 and
asked if low noise road surfacing would include the A1089. The
Senior Consultant replied that the A1089 would not be included as
it did not form part of the LTC scheme, and some parts of the local
road network could not use low noise road surfacing due to safety
issues, for example some roads which were curved required anti-skid
road surfacing to reduce the number of accidents. Councillor
Muldowney asked for officers to push for low noise road surfacing
on the A1089 as the LTC would increase traffic on this road due to
the ports. The Interim Assistant Director Regeneration and Place
Delivery stated that the team could push for this as part of RIS3
consultation, but it was outside the remit of the LTC scheme. He
asked residents who wished for low noise road surfacing on the
A1089 to lobby their local Councillors, MPs and the Department for
Transport as this would have an impact when the Council came to
make representations as part of RIS3.
Councillor Muldowney questioned the use of carbon hubs and measure
L23 and asked how much money this would bring into the Council. The
Interim Assistant Director Regeneration and Place Delivery stated
that NH were currently looking at ways to establish local
businesses to invest in low carbon technologies, which would form
part of the carbon hubs. He stated that there was currently no
clear definition for a carbon hub, but it recognised NH need to
reduce the carbon impact of the route. He stated that Thurrock
Council were currently in negotiation regarding L23 with NH, as NH
would be saving money by using the local road network such as the
A13 to connect to the LTC, rather than developing a whole new
interchange. He stated that the Council were therefore asking for
this saving by NH to be recognised and monies supplied to Thurrock
for this. He stated that there was no estimated cost at this stage,
and no clear response from NH or the Department for Transport had
yet been received.
The Resident Representative asked for an update on measure L18. The
Senior Consultant replied that Thurrock officers were currently
preparing a technical paper on the East Tilbury landfill site,
which would contain all the necessary information regarding
ecology, history, contamination and ownership. He stated that the
paper highlighted that invertebrates of national importance were
likely to be located on the site, and Natural England maybe
considering categorising the area as a Site of Special Scientific
Interest (SSSI). He added that the team were unsure of what was
under the site as no boreholes had been carried out due to safety
concerns. The Chair stated that a large area of the London Resort
had been designated as an SSSI and asked how this had impacted that
scheme. The Senior Consultant replied that not much work had been
undertaken on the scheme since this designation.
Supporting documents: