Agenda item

Stanford Le Hope Transport Projects

Minutes:

Following the request from the Chair, Councillor Rice, for a report to be provided on the Stanford Le Hope Transport Project, to include the £7 million spend on consultants and how that £7 million was financed and what was achieved and who had authorised this and to inform Members on the price for the Old Brewery to accommodate the parking and waiting areas for buses and coaches going to DP World.  Andy Millard, Director of Place, introduced the report by referring Members to the report that provided the introduction and background to the project and the Issues and Options that included costs of the Old Brewery Site.

 

Councillor Rice questioned whether there was an overall figure that had been expended on consultants through the period of the project so far. Anna Eastgate stated there was not an overall figure on what was spent on the consultancy but £7 million had been spent on the project to date which included project management resource and was the original design and build contract that had been procured at the start of the project.

 

Councillor Rice asked for an estimate as to when the project would be completed. Anna Eastgate stated that the Council were in detailed design stage, there would now be two phases – phase 1 going out to market on a fixed price tender and anticipated that completion of the station site would be summer 2021 then in parallel once phase 1 was up and running, phase 2 would start on the design and commence with the old brewery site being used as the construction compound. Therefore once phase 1 was completed, subject to planning approval, work would commence on the construction for the phase 2 works. With no final completion date available for phase 2 as the designs had not been development sufficiently to understand what the programme for that would be, but as these would be general civil works should be completed in a relatively short period of time.

 

Councillor Spillman asked for reassurance on behalf the residents of Stanford Le Hope that this project would finally get sorted out. Anna Eastgate spoke with confidence that the project following the acquisition of the old brewery site had given this project a whole new opportunity to deliver something substantially better than what was originally proposed. The revision to the scheme had given the Council the opportunity to acquire an asset and improve facilities for local people including additional car parking. That a Project Steering Group had been set up with key stakeholders such as the ward members, key stakeholders and resident representatives who had local knowledge and had a valuable contribution to make in helping to shape those proposals. This had already been acknowledged by Councillors Hebb and Piccolo as a positive step and had every confidence that the project team would bring this project forward.

 

Councillor Rice stated that the project was needed and welcomed with the potential expansion of DP World.

 

Councillor Rice requested that this report be presented at this committee on a quarterly basis.

 

Anna Eastgate informed Members that the Council was in the process of setting up on-line registerable newsletter and information of this would be posted in the station and within that facility. This would enable residents and commuters to receive updates on the project, the project web site was being updated to improve the level of information being provided and making it more accessible to the community.

 

RESOLVED

 

1.         That the Standard and Audit Committee noted and commented on the report content.

 

2.         That the Stanford Le Hope Transport be scheduled onto the work programme to be presented at every quarterly meeting.

 

Supporting documents: