Agenda item

Grays Town Centre Update

Minutes:

Presented by Anna Eastgate, the report provided an update to Members about the changes to traffic management in Grays Town Centre and the reintroduction of two-way traffic in Orsett Road that was the final part of phase 2 of the Grays town centre traffic management improvements project. An enquiry inbox for the project had been set up and was monitored. Officers had walked around the temporary traffic diversions in place (whilst the project were underway) to ensure the signage was correct. There had been some miscommunication with residents on Bedford Road regarding resident parking which had been resolved.

 

The Chair questioned whether residents and businesses had been warned of the level of disruption from the forthcoming works. Anna Eastgate replied that residents had been warned in October 2019 with the two dates of the works due to take place which was initially 6 January 2020 but had been moved to the week after due to traffic management issues. There were not many complaints regarding the notice of works but complaints were focussed more on the congestion caused by the works and by people driving the wrong way on a one way signed road. The service was working with the police to enforce the signs in place. However, traffic flow usually settled after people became used to the signage.

 

The Chair said that Grays town centre could not afford to lose its economic activity and queried whether businesses had the opportunity to give their views on the project. Anna Eastgate answered that there had been a complaint from a business owner on Clarence Road in Grays which had been in regards to the owner finding difficulty in getting the vehicle out onto the road but the traffic diversion had not affected his business itself.

 

Councillor Gerrish questioned the target end date for the project and if the traffic diversion would be removed in parts or in its entirety. For completion of physical works, Anna Eastgate said that the aim was for the week commencing 30 March 2020. Once works were completed, the traffic diversion would be removed in its entirety. A SCOOT (Split Cycle Offset Optimisation Technique) traffic system would be implemented following on from this in April 2020.

 

Peter Wright explained that a SCOOT traffic system was generally used in London and one was in place at the Treacle Mine roundabout. The SCOOT traffic system analysed the traffic flow through loops installed underground and traffic lights were manipulated according to the traffic situation. For the system to work in Grays town centre, the traffic flow and patterns had to settle before it could be implemented therefore traffic would run on fixed time traffic lights until the end of April 2020.

 

The Vice-Chair commented on the efficiency of the SCOOT traffic system on the Treacle Mine roundabout. In response, Peter Wright said that the system worked to the best of its ability but the Treacle Mine roundabout had become a series of junctions as opposed to being a roundabout. The issue was one of capacity rather than the system itself.

 

RESOLVED:

 

1.1       That Committee commented on the update of the project progress.

Supporting documents: