Venue: Council Chamber, Civic Offices, New Road, Grays, RM17 6SL
Contact: Lucy Tricker, Senior Democratic Services Officer
Email: direct.democracy@thurrock.gov.uk
Media
Items
No. |
Item |
14. |
Minutes PDF 88 KB
To approve as a correct record the minutes of
the Lower Thames Crossing Task Force meeting held on 14 November
2022.
Additional documents:
Minutes:
The minutes of the meeting held on 14 November
2022 were approved as a true and correct record.
|
15. |
Items of Urgent Business
To receive additional items that the Chair is
of the opinion should be considered as a matter of urgency, in
accordance with Section 100B (4) (b) of the Local Government Act
1972.
Additional documents:
Minutes:
There were no items of urgent business.
|
16. |
Declaration of Interests
Additional documents:
Minutes:
There were no interests declared.
|
17. |
Thames Crossing Action Group Presentation PDF 3 MB
Additional documents:
Minutes:
The Thames Crossing Action Group (TCAG)
Representative introduced her presentation which can be found at
the following weblink:
https://democracy.thurrock.gov.uk/documents/s37884/Thames%20Crossing%20Action%20Group%20Presentation.pdf
.
The TCAG Representative explained that the group had been founded
by residents to represent those opposed to the scheme, including
residents in Kent and across the country. She explained that in
2017 TCAG had been refused a question at Full Council, and there
had been much media and press attention surrounding this. She
stated that the LTC Task Force had then been set up to improve
communications between officers, Members, and residents. She
explained why TCAG were fighting the scheme, such as problems on
the Dartford Crossing that would not be improved by a new crossing,
problems during construction phase, and increased pollution. She
explained that issues with the design of the LTC, such as a single
lane on the A2 slip road and the ‘Stanford detour’, as
well as a lack of traffic migration data during design phase, could
also increase problems for users of the road and residents. She
added that a new crossing could also increase cross-river traffic
by 50%, and would have a negative impact on nearby homes, farms,
greenbelt land and the solar farm.
The TCAG Representative moved on and stated that in 2016 the cost
of the scheme had been approximately £4bn, but this is now
officially estimated to be up to £9bn+ (with many believing
it would end up being £10bn+++) and meant that the Benefit
Cost Ratio had fallen from 3.1 to 1.22. She explained that the
recently announced two-year delay would continue to increase costs
and therefore reduce the Benefit Cost Ratio. She added that
additional works that would be needed as a direct result of the LTC
(if it goes ahead) and/or projects originally proposed by National
Highways to be included in the project, such as the Tilbury Link
Road, Blue Bell Hill, and A2 dualling were no longer being
considered as part of the project, but instead progressed as
stand-alone projects, which many consider to be a false economy.
The TCAG Representative explained that the Accounting Officer
Assessment had been published in January 2023, but this document
was using cost data from August 2020, which was now outdated. She
added that this document contained references to an independent
assessment review which had been carried out, and TCAG had entered
a Freedom of Information Request to see this document. She stated
that the request had been refused by Cabinet. She stated that TCAG
had therefore instructed solicitors and were currently waiting on a
response.
The TCAG Representative moved on to share
evidence that if the LTC did go ahead, carbon output would increase
both during the construction and operation phase. She explained
that a legal challenge had recently been put to the
government’s Net Zero policy, and the government had a
deadline of 31 March 2023 to respond to this challenge. She added
that other legal challenges were also ongoing. She then commented
on aspects considered greenwashing and propaganda. The
...
view the full minutes text for item 17.
|
18. |
Verbal Update: Council's Position - Examination
Additional documents:
Minutes:
The Director of Place updated the LTC Task
Force and stated that he had started at Thurrock Council in July
2022, and had become Director of Place in October 2022, and
therefore the LTC response fell under his remit. He stated that he
begun his work by seeking clarity on the LTC, the cost to the
council, and how the government intervention in September 2022, and
subsequent S114 notice in December 2022, would affect the project.
He explained that at no point had funding been withdrawn, but the
Council had to understand the full cost of the project and confirm
there was sufficient money in the budget under the S114 notice to
progress a compliant response. He stated that some of the design
team had paused some of their work in the meantime.
The Director of Place explained that the Planning Performance
Agreement (PPA) technically stopped at DCO submission, so no formal
funding structure had been in place and the current Council funding
was not sufficient. He explained that therefore the team had sought
a better deal from National Highways and had got this in writing,
so work on the response was now progressing. He explained that as
Thurrock Council was a host authority, it was automatically
registered as an interested party, but the Council had confirmed
with the Planning Inspectorate that they would be making
representation at the examination phase. He stated that the team
had asked the Planning Inspectorate to consider extending the
pre-examination phase by three months to ensure all information is
correctly considered, and the Council were currently waiting on a
response to this request. The Director of Place explained that
there had also been a change to project management staffing, as the
planning and transport teams within the Council were now more
engaged with the process, although consultancy experts remained
involved. He thanked the consultants for their hard work throughout
the process.
Councillor Ononaji questioned how much the project had cost the
Council to date. The Director of Place explained that it was hard
to find an exact figure due to the nature of the project, but
estimated that consultancy cost and officer time had cost
approximately £1.4-1.5m, although 40% of this had been
covered by the PPA. He stated that more was now covered by the PPA,
and this meant that cost would approximately be between
£400,000 and £500,000. The TCAG Representative
questioned if legal representation was covered by the PPA, and if
the LTC administration team were still working and reviewing the
DCO documents. The Director of Place explained that legal
representation costs had been included in the Council’s
budget, but were not covered by the PPA from National Highways. He
added that administration had previously been supplied through an
external team, with no oversight from council officers, but now
additional Council administration officers would be used to support
the external team, and would be tasked with processes such as
checking invoices. He added that consultants engaged through
Stantec still remained working with ...
view the full minutes text for item 18.
|
19. |
Work Programme PDF 70 KB
Additional documents:
Minutes:
Members did not have any items to add to the
Work Programme.
The Chair thanked Members, officers, and co-opted members for their
hard work on the Task Force throughout the 2022/23 municipal
year.
|